QUESTION NO: 1
What is the definition of project plan execution?
A. Integrating all planned activities.
B. Performing the activities included in the plan.
C. Developing and maintaining the plan.
D. Execution of deliverables.

Answer: B

QUESTION NO: 2

Information distribution involves making needed information available to project stakeholders in a timely manner. What is an output from information distribution?

A. Earned value analysis
B.
Trend analysis
C. Project records
D. Performance reviews

Answer: C 


QUESTION NO: 3
Scope verification is PRIMARILY concerned with which of the following?

A. Acceptance of the work deliverables.
B. Accuracy of the work deliverables.
C. Approval of the scope statement.
D. Accuracy of the work breakdown structure.


Answer: A